A profitable month can hide a job that’s losing money. The work-in-progress schedule is where that shows up first, if you know how to read it.
Construction revenue doesn’t follow invoices. On a long job, billing can run well ahead of the work or well behind it, so a P&L built on billings alone can make a month look better or worse than it really was. The work-in-progress (WIP) schedule fixes that by measuring each open job on its own: how far along it is, what it has earned, what it has billed, and what it’s now expected to make. Banks and bonding companies routinely ask for it, for the same reason.
| Job | Contract | Est. total cost | Cost to date | % complete | Earned revenue | Billed to date | Over/(under) |
|---|---|---|---|---|---|---|---|
| Job A | $1,000,000 | $800,000 | $400,000 | 50% | $500,000 | $560,000 | $60,000 |
| Job B | $600,000 | $480,000 | $360,000 | 75% | $450,000 | $400,000 | ($50,000) |
| Job C | $400,000 | $390,000 | $195,000 | 50% | $200,000 | $220,000 | $20,000 |
Illustrative figures. Percent complete = cost to date ÷ estimated total cost. Earned revenue = contract × percent complete.
Job A has billed $60,000 more than it has earned. That cash is welcome, but it isn’t profit; it’s a liability (“billings in excess of costs and estimated earnings,” a contract liability under ASC 606) because the work still has to be done. Some overbilling is normal and healthy. Spending it on overhead or the next job is how contractors end up short of cash when the remaining work comes due.
Job B has earned $50,000 more than it has billed. That’s recorded as an asset (“costs and estimated earnings in excess of billings,” a contract asset), but it’s worth asking why. Sometimes billing is simply lagging. Sometimes it’s an unapproved change order, or costs running ahead of the estimate, which inflates percent complete. Large or growing underbillings are one of the first things a surety looks at.
Job C was bid at $320,000 of cost, a 20% margin. The estimate to complete has since risen, and estimated total cost is now $390,000. Expected gross profit has fallen from $80,000 to $10,000, a margin of 2.5%, and at 50% complete the job has earned only $5,000 of gross profit to date. If the estimate to complete isn’t updated, none of this reaches the P&L until the job closes out and the overrun lands all at once. Updating every job’s estimate and comparing its current margin with the original bid, every cycle, is what turns a WIP schedule into an early warning.
If the estimate ever shows a job will lose money overall, the full expected loss is recognized right away, not spread over the rest of the job. That’s another reason the estimate to complete has to be kept current.
WIP schedules, estimated cost to complete, and over/under billing exposure are standard in every construction engagement, refreshed on each reporting cycle. See our construction reporting →